Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q81: A contractor's project being analyzed by PERT
Q90: In a PERT network, non-critical activities that
Q93: A project being analyzed by PERT has
Q104: Given the critical path below,calculate the following:
a.The
Q110: PERT calculations typically include the duration variance
Q112: In project management, crashing an activity must
Q116: Which of the following statements regarding time-cost
Q120: If an activity whose normal duration is
Q121: Which of the following is NOT performed
Q129: _ is decreasing activity time in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents