Three processes are involved in the manufacturing of Chemical Z.First,the raw mixture goes through the Mixing Process,then the Heating Process,and finally the Bottling Process.The hourly production capacity of the three processes is 400 units,600 units and 400 units respectively.Assume that a recent process improvement has resulted in a 20 per cent increase in the capacity of the Bottling Process.This process improvement will:
A) Increase the production of Chemical Z by 80 units per hour
B) Increase the production of Chemical Z by 120 units per hour
C) Increase the production of Chemical Z by 200 units
D) Have no effect on the production level per hour
Correct Answer:
Verified
Q63: Three processes are involved in the manufacturing
Q64: Lazy Linda Ltd manufactures small kitchen appliances.
Q68: Which of the following statements about throughput
Q72: Lazy Linda Kitchen Appliances manufacturers small kitchen
Q73: Lazy Linda Kitchen Appliances manufacturers small kitchen
Q77: Lazy Linda Kitchen Appliances manufacturers small kitchen
Q78: Lazy Linda Kitchen Appliances manufacturers small kitchen
Q85: Quality costs―failure, prevention and appraisal―can be graphed
Q88: When a company uses an activity-based management
Q90: If a firm needs to identify the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents