If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days) for all jobs is (assume zero for today's date)
A) 16.4 days.
B) 22.6 days.
C) 28.7 days.
D) 33.0 days
Correct Answer:
Verified
Q67: Four products (1,2,3,and 4)must be processed on
Q68: If the following jobs are sequenced according
Q69: If the following jobs are sequenced according
Q70: The following set of jobs must be
Q71: If the following jobs are sequenced according
Q73: If the following jobs are sequenced according
Q74: The scheduling rule that minimizes the makespan
Q75: Four products (1,2,3,and 4)must be processed on
Q76: If the following jobs are sequenced according
Q77: Four products (1,2,3,and 4)must be processed on