The following set of jobs must be processed serially through a two-step system.If Johnson's Rule is used to sequence the jobs then the order in which the jobs would be performed is
A) A-B-C-D-E
B) C-B-E-D-A
C) E-B-D-A-C
D) D-E-B-A-C
Correct Answer: