Atlas Inc.produces product A and product B.Each product must go through two processes.Each A produced requires two hours in process 1 and five hours in process 2.Each B produced requires six hours in process 1 and three hours in process 2.There are 80 hours of capacity available each week in each process.Each A produced generates $6.00 in profit for the company.Each B produced generates $9.00 in profit for the company.If the company produces 6 units of A and 9 units of B the amount of slack (in hours) for process 1 is
A) 0 hours.
B) 14 hours.
C) 66 hours.
D) 80 hours.
Correct Answer:
Verified
Q20: Atlas Inc.produces product A and product B.Each
Q21: A company produces product A and product
Q22: Briefly define the components that comprise a
Q23: A company produces product A and product
Q24: For a less than or equal to
Q26: The constraint 3x1 + 6x2 > 48
Q27: TicToc produces product A and product B.These
Q28: TicToc produces product A and product B.These
Q29: Atlas Inc.produces product A and product B.Each
Q30: The area that contains the values that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents