A project consists of the following four activities with activity times in days:
Table YY
-Using Table YY,the earliest start (ES) time for activity B is
A) 5 days.
B) 6 days.
C) 11 days.
D) 14 days.
Correct Answer:
Verified
Q64: A project consists of the following four
Q65: A project consists of the following activities:
Q66: A project consists of the following four
Q67: A project consists of the following four
Q68: The _ probability distribution is typically used
Q70: The following table of probabilistic time estimates
Q71: The estimated variance for an activity with
Q72: The slack time for an activity can
Q73: The estimated variance for an activity with
Q74: The estimated mean time for an activity