A contractor builds large ships for the Department of Defense.A recent contract called for 12 amphibious landing platforms.It was originally estimated that the first of these would cost $1 billion and that 80 percent learning would be appropriate.In fact,the first ship cost $1.6 billion and the second $1.12 billion.What is the revised learning curve? What will be the total cost of the twelve ships? Is it higher or lower than the original estimate? If the defense department cuts the contract from 12 ships to 9,what happens to the average cost per ship?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q81: A company is preparing a bid on
Q85: The fourth unit of production took 80
Q89: Using the doubling approach,determine how long it
Q89: Joe's Manufacturing is considering bidding on a
Q90: The first unit took 79 hours; the
Q91: A product was priced assuming an 80%
Q94: A small manufacturer that offers "hand crafted"
Q98: Your firm has expertise with a special
Q102: A firm that successfully pursues a steeper-than-industry-average
Q106: The seventh unit of production took 63.423
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents