The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client.Accordingly,she has estimated the time it should take for each of her top consultants-Charlie,Gerald,Johnny,and Rick-to complete any of the four projects,as follows:
(a)What is the total number of hours required by the following arbitrary assignment?
Charlie→B;Gerald→A;Johnny→D;Rick→C
(b)What is the optimal assignment of consultants to projects? (Use the assignment method. )
(c)For the optimal schedule,what is the total number of hours it will take these consultants to complete these projects?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q43: What is the difference between a Gantt
Q51: _ are planning charts used to schedule
Q54: Johnson's rule sequences a set of jobs
Q57: Earliest due date is a shop floor
Q59: What is input-output control?
Q65: Eight jobs have been sequenced at a
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q68: Which of the following dispatching rules ordinarily
Q77: Which of the following is an advantage
Q99: The priority rule that appears fair to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents