Five jobs are waiting for processing through two work centers.Their processing time (in minutes) at each work center is contained in the table below.Each job requires work center Alpha before work center Beta.According to Johnson's rule,what is the optimum sequence of jobs and the minimum time for completion of all jobs?
A) V-T-S-U-R;225
B) U-R-T-S-V;175
C) R-S-T-U-V;240
D) U-S-V-T-R;200
E) R-U-T-S-V;175
Correct Answer:
Verified
Q65: Eight jobs have been sequenced at a
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q68: Five jobs are waiting to be processed.Their
Q69: Which of the following dispatching rules tends
Q73: Which critical ratio value implies that a
Q74: What is the priority rule that sequences
Q77: Which of the following is an advantage
Q87: _ determines the order in which jobs
Q88: _ determine the sequence of jobs in
Q99: The priority rule that appears fair to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents