Consider the simple 3-station assembly line illustrated below,where the 2 machines at Station 1 are parallel,i.e. ,the product only needs to go through one of the 2 machines before proceeding to Station 2. What is the throughput time of this process?
A) 12 min.
B) 20 min.
C) 38 min.
D) 18 min.
E) 58 min.
Correct Answer:
Verified
Q43: In "drum,buffer,rope," what provides the schedule,i.e.the pace
Q45: Which of the following techniques is NOT
Q48: In "drum,buffer,rope," the _ acts like signals
Q49: Fixed costs are those costs that continue
Q50: Consider the assembly line below.The three fabrication
Q51: Consider the simple 3-station assembly line illustrated
Q166: Explain the importance of a bottleneck operation
Q171: The Theory of Constraints (TOC) strives to
Q193: Break-even is the number of units at
Q198: Which of the following statements regarding fixed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents