The network below represents a project being analyzed by the critical path method.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q61: Explain why the critical path is the
Q62: The critical path for the network activities
Q65: A network consists of the activities in
Q66: What are the earliest activity start time
Q68: Given the project within the table below,calculate
Q69: Draw the AOA and AON networks for
Q71: The critical path for the network activities
Q73: Define slack time.
Q74: What is the objective of critical path
Q96: The time an activity will take assuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents