Bienestar, Inc., has done a cost analysis for its production of vests. The following activities and cost drivers have been developed: Activity Cost Formula
Maintenance $11,000 + $2 per machine hour
Machining $55,000 + $3 per machine hour
Inspection $70,000 + $500 per batch
Setups $2,000 per batch
Purchasing $80,000 + $150 per purchase order
Following are the actual costs of producing 75,000 vests: 5,000 machine hours; 10 batches; 20 purchase orders What is the budget variance for total costs in an activity-based performance report?
A) $1,000 F
B) $2,000 F
C) $3,000 F
D) none of these
Correct Answer:
Verified
Q166: Bienestar, Inc., has done a cost analysis
Q167: Villanova, Inc., has done a cost analysis
Q168: Silver Faces, Inc., has done a cost
Q169: The ideal budget system creates
A) extreme caution
Q171: Silver Faces, Inc., has done a cost
Q172: Villanova, Inc., has done a cost analysis
Q173: Villanova, Inc., has done a cost analysis
Q174: Bienestar, Inc., has done a cost analysis
Q175: When budgets are used to evaluate performance,
Q175: Bienestar, Inc., has done a cost analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents