Setup time for a product is 12 hours. A firm that uses JIT and produces the same product has reduced setup time to 1 hour. Setup labor is $6 per hour. The non-value-added costs are
A) $72.
B) $66.
C) $12.
D) $6.
Correct Answer:
Verified
Q28: For nonvalue-added activities that are unnecessary, the
Q76: A time-and-motion study revealed that it should
Q78: Which of the following focuses on the
Q79: Value-added costs equal standard quantity times
A)non-value-added costs.
B)currently
Q80: Alpha, Inc., manufactures Product A. The setup
Q82: Your company keeps 15 days of materials
Q83: The continuous improvement subcycle of Kaizen costing
Q84: The maintenance subcycle is defined by what
Q85: Controlling the cost reduction process using Kaizen
Q86: A company has 5 days of finished