Figure 15-2
The following information relates to Cranmore Manufacturing: To produce a unit of product:
Cutting department 5 minutes per unit
Welding department 8 minutes per unit
Polishing department 3 minutes per unit
Finishing department 4 minutes per unit
There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes.
-Refer to Figure 15-2. What is the cycle time of operation?
a. 60 minutes
b. 20 minutes
c. 35 minutes
d. 16 minutes
Correct Answer:
Verified
Q24: The difference between the total profit change
Q27: Which is NOT a benefit of lean
Q31: The achievement of _ efficiency and _
Q32: The quantitative assessment of productivity changes is
Q43: To identify value streams using a two-dimensional
Q45: Figure 15-1
The following information relates to Lancashire
Q47: The new product value stream focuses on
A)developing
Q48: The worth of one or more features
Q54: Identification of a "value stream," pursuit of
Q58: The processing department can produce one unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents