Figure 15-2
The following information relates to Cranmore Manufacturing: To produce a unit of product:
Cutting department 5 minutes per unit
Welding department 8 minutes per unit
Polishing department 3 minutes per unit
Finishing department 4 minutes per unit
There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes.
-Refer to Figure 16-2. What is the production rate?
A) 12 units per hour
B) 20 units per hour
C) 15 units per hour
D) 7.5 units per hour
Correct Answer:
Verified
Q41: Reducing the time it takes to configure
Q42: The departments or cells which contain all
Q43: To identify value streams using a two-dimensional
Q43: There are two basic types of non-value
Q45: Figure 15-1
The following information relates to Lancashire
Q47: The new product value stream focuses on
A)developing
Q51: Figure 15-1
The following information relates to Lancashire
Q53: The production rate
A) tells how many units
Q54: Identification of a "value stream," pursuit of
Q58: The processing department can produce one unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents