Lampost Manufacturing provides the following information: To produce a unit of product:
Mixing department 4 minutes per unit
Molding department 7 minutes per unit
Casting department 9 minutes per unit
Finishing department 5 minutes per unit
There is a wait time of 5 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 8 minutes.
Required:
a. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
b. What is the bottleneck department?
c. What is the production rate? What is the cycle time of operation?
d. What would be the time to produce the first unit under a cellular manufacturing setup?
Correct Answer:
Verified
a.
Process time...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q121: The component which provides a series or
Q136: Information about Bodacious Corporation is as follows:
Q138: At the end of 2014, Diatomic Company
Q139: Information about Bodacious Corporation is as follows:
Q140: Information about Taekwondo Corporation is as follows:
Q143: Listed below are several possible combinations for
Q144: At the end of 2014, Cardigan Corporation
Q145: The Kristofferson Company provides the following information:
Q149: Explain the difference between technical and input
Q153: In calculating the profit linkage, PQ represents
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents