Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line.The schedule requires 80 ovens in an 8-hour day.The assembly includes seven tasks.The table below indicates the performance time and the sequence requirements for each task.
(a)What is the cycle time for this assembly operation?
(b)What is the theoretical minimum number of workstations?
(c)Draw the precedence diagram.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q121: A company is designing a product layout
Q122: Four hundred and eighty minutes of production
Q135: An assembly line consists of 158 tasks
Q283: If a layout problem is solved by
Q286: Which of the following is a common
Q296: Which of the following is NOT a
Q301: Explain what the purpose of assembly-line balancing
Q307: Assembly line balancing has just been used
Q310: Identify the five common layout heuristics used
Q319: What are the advantages and disadvantages of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents