An electronics manufacturer makes remote control devices for interactive-cable-TV systems.The following assembly tasks must be performed on each device.
a.Draw the precedence diagram for this problem.
b.What is the sum of the task times?
c.What cycle time will allow the production of 200 units over a ten-hour day?
d.What is the theoretical number of workstations needed?
e.Balance this assembly line using the heuristic most following tasks and the heuristic longest operation time.
f.How do these two solutions differ? Which do you prefer;why?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q132: You have been asked to balance a
Q132: An assembly line consists of 21 tasks
Q134: A firm operates a flow shop building
Q135: An assembly line consists of 158 tasks
Q137: An assembly line has been designed to
Q286: Which of the following is a common
Q296: Which of the following is NOT a
Q301: Explain what the purpose of assembly-line balancing
Q308: _ is the maximum time that the
Q315: Identify the formulas for the following terms
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents