Which of the following statements regarding PERT times is true?
A) The optimistic time estimate is an estimate of the minimum time an activity will require.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) .
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:
Verified
Q90: In a PERT network, non-critical activities that
Q91: An activity on a PERT network has
Q92: A project being analyzed by PERT has
Q93: A project being analyzed by PERT has
Q97: Contract requirements state that a project must
Q98: An activity on a PERT network has
Q99: The beta distribution is used in project
Q100: A local project being analyzed by PERT
Q101: A project whose critical path has an
Q101: Consider the network described in the table
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents