A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?
A) 0.0228
B) 0.3446
C) 0.6554
D) 0.9772
E) 18
Correct Answer:
Verified
Q88: Which of the following statements regarding PERT
Q89: A PERT project has 45 activities,19 of
Q90: In a PERT network, non-critical activities that
Q91: An activity on a PERT network has
Q92: A project being analyzed by PERT has
Q96: Which of the following statements regarding PERT
Q97: Contract requirements state that a project must
Q98: An activity on a PERT network has
Q100: Which of the following statements regarding PERT
Q101: A project whose critical path has an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents