A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days.The sum of all activity variances is 81;the sum of variances along the critical path is 64.What is the probability that the project will take 130 or more days to complete?
A) 0.1057
B) 0.1335
C) 0.8512
D) 0.8943
E) 1.29
Correct Answer:
Verified
Q76: The network below represents a project being
Q78: Consider the network presented in the following
Q79: A network consists of the following list.Times
Q80: The PERT pessimistic time estimate is an
Q84: The beta distribution is used in project
Q85: An activity on a PERT network has
Q89: The _ distribution is used by PERT
Q105: The _ distribution is appropriate for calculating
Q108: A project whose critical path has an
Q110: PERT calculations typically include the duration variance
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents