Table J.3
Six jobs have just arrived at workstation 017;which has been idle.All the pertinent data are given in the following table.The shop works eight hours per day.It is now time zero.
-Use the information in Table J.3.According to the critical ratio (CR) rule,which one of following sequences is most appropriate?
A) F-A-D-B-E-C
B) D-B-F-E-A-C
C) A-B-D-F-E-C
D) C-D-F-B-A-E
Correct Answer:
Verified
Q31: When choosing a priority sequencing rule:
A) select
Q36: Table J.2
Suppose that the following six jobs
Q38: Table J.2
Suppose that the following six jobs
Q38: Table J.1
The framing department has six jobs
Q40: Table J.1
The framing department has six jobs
Q40: Table J.2
Suppose that the following six jobs
Q41: Table J.4
Workstation 1 has five jobs waiting
Q42: Table J.3
Six jobs have just arrived at
Q42: Table J.5
The following three jobs just arrived
Q44: Table J.4
Workstation 1 has five jobs waiting
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents