Table J.12
Consider the following problems in which six jobs must each be processed on two machines starting with machine 1 and then going to machine 2.The following processing times and due dates are in hours.
-Use the information in Table J.12.What sequence would you use if you wanted to minimize the makespan of the jobs?
A) A-C-E-B-D-F
B) B-F-D-E-C-A
C) C-F-A-E-B-D
D) C-D-B-A-F-E
Correct Answer: