A quality manager has established a sampling plan that calls for a sample size of 75 units and an acceptance number of 2.The supplier has agreed to a contract that calls for an AQL of 0.02 and an LTPD of .04.What is the probability of accepting the lot if the actual percentage of defective is 3%? Table G.1 is appended to this exam.
A) less than 0.63
B) between 0.63 and 0.66
C) between 0.66 and 0.69
D) greater than 0.69
Correct Answer:
Verified
Q24: A quality manager has established a sampling
Q27: A quality manager has established a sampling
Q30: Which one of the following alternatives will
Q33: A double-sampling plan has n1 = 50,n2
Q34: Which one of the following will increase
Q36: Which one of the following actions will
Q38: A double-sampling plan has n1 = 50,n2
Q45: A single-sampling plan by attributes is needed
Q50: If the sample size is increased and
Q64: A quality manager has established a sampling
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents