Scenario 9.9
Demand = 5,200 units/year
Standard deviation of weekly demand = 11 units
Ordering costs = $45/order
Holding costs = $2/unit/year
Cycle-service level = 90% (z for 90% = 1.28)
Lead-time = 3 weeks
Number of weeks per year = 52 weeks
-Use the information in Scenario 9.9.If a firm uses the continuous review system to control the inventory,what would be the reorder point?
A) 0 units
B) greater than 0 but less than or equal to 300 units
C) greater than 300 but less than or equal to 600 units
D) greater than 600 units
Correct Answer:
Verified
Q132: Your firm uses a continuous review system
Q133: Cynthia Korinsky,manager of a large medical supply
Q134: Scenario 9.7
You are the operations manager of
Q135: Scenario 9.7
You are the operations manager of
Q136: Scenario 9.7
You are the operations manager of
Q138: Scenario 9.10
Demand = 52,000 units/year
Standard deviation of
Q139: Scenario 9.10
Demand = 52,000 units/year
Standard deviation of
Q140: Scenario 9.11
The Hastings Company is a nation-wide
Q141: Scenario 9.13
Demand = 100,000 units/year
Number of days
Q142: Scenario 9.12
Demand = 50,000 units/week
Standard deviation of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents