Table 7.8
King Supply makes four different types of plumbing fixtures: W,X,Y and Z.The contribution margins for these products are: $70 for Product W,$60 for Product X,$90 for Product Y and $100 for Product Z.Fixed overhead is estimated at $5,500 per week.The manufacture of each fixture requires four machines,Machines #1,2,3 and 4.Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other.The processing requirements to make one unit of each product are shown in the table.Weekly product demand for the next planning period has been forecasted as follows: 70 Ws,60 Xs,50 Ys and 30 Zs. In the questions that follow,the traditional method refers to maximizing the contribution margin per unit for each product,and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 7.8.Using the bottleneck method,in what sequence should products be scheduled for production?
A) Z,Y,X,W
B) X,W,Z,Y
C) Z,Y,W,X
D) X,Y,Z,W
Correct Answer:
Verified
Q49: In a drum-buffer-rope system, the lot size
Q85: Balance delay could be described as the:
A)
Q91: Table 7.7
A company makes four products that
Q94: Which one of the following statements is
Q95: What is the definition of "theoretical maximum
Q97: Table 7.8
King Supply makes four different types
Q99: Table 7.8
King Supply makes four different types
Q100: A line balance that is 100% efficient
Q101: Figure 7.1 Q111: Which one of the following statements about
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents