Table 7.11
The Pennsylvania Appliance Company is installing an assembly line to produce vacuum cleaners,and you,as an operations manager,are responsible for balancing the line.The work elements to be performed are listed,along with their times and immediate predecessors.
-Use the information in Table 7.11.The company is planning to operate 2 shifts per day 8 hours per shift.If the desired output rate of the line is 480 units per day,what is the theoretical minimum number of stations (TM) for the line? How many workstations are needed for the most efficient balance possible given these circumstances?
A) TM = 3;solution = 3 stations
B) TM = 3;solution = 4 stations
C) TM = 4;solution = 4 stations
D) TM = 4;solution = 5 stations
Correct Answer:
Verified
Q102: Table 7.12
A company desires to set up
Q103: Table 7.10
Balance the following line for an
Q104: Table 7.13
The following information is given about
Q105: Table 7.11
The Pennsylvania Appliance Company is installing
Q106: Table 7.12
A company desires to set up
Q108: Table 7.14
The production of a particular product
Q109: Table 7.9
Balance the following line for an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents