Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.
Correct Answer:
Verified
Q3: Following the project defining and organizing phase,
Q6: Project managers should be able to organize
Q7: Projects, and the application of project management,
Q13: What are the primary responsibilities of a
Q14: Projects often cut across organizational lines.
Q21: Which one of the following best describes
Q26: Figure 7.1 Q27: Figure to accompany Table 7.1 Q28: A critical path is any sequence of Q39: Figure 7.1
![]()

![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents