Fig.2.1
-For the network shown in Fig.2.1,what is the project duration?
A) 6
B) 15
C) 13
D) 14
Correct Answer:
Verified
Q4: In a network diagram, an activity:
A) is
Q5: The work breakdown structure is a statement
Q10: A project is an interrelated set of
Q21: Which one of the following best describes
Q24: Figure to accompany Table 2.1
Q26: Figure to accompany Table 2.1
Q27: Figure to accompany Table 2.1
Q50: A project manager should stop crashing a
Q84: The optimistic time is the probable time
Q102: When using the beta distribution for estimating