Table 2.6 -Disaster Strikes and Activity F Takes 20 Days Instead of 20

Question 66

Multiple Choice

Table 2.6
Table 2.6    -Disaster strikes and activity F takes 20 days instead of the anticipated 5 days.Using Table 2.6,how much longer will the project last than initially estimated? A) 15 days B) 0 days C) 7 days D) 3 days
-Disaster strikes and activity F takes 20 days instead of the anticipated 5 days.Using Table 2.6,how much longer will the project last than initially estimated?


A) 15 days
B) 0 days
C) 7 days
D) 3 days

Correct Answer: