Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 2.14,what is the critical path and expected completion time for this project?
A) A-D-E;17 weeks
B) A-C;18 weeks
C) B-E;14 weeks
D) A-D-E;18 weeks
Correct Answer:
Verified