Which of these is NOT one of the four categories of project risk?
A) cost/benefit
B) operations
C) strategic fit
D) project team capability
Correct Answer:
Verified
Related Questions
Q104: Table 7.3 Q105: In making an estimate of the most Q106: Table 7.2 Q107: Table 7.3 Q109: Table 7.14 Q111: Following are four sets of most optimistic, Q112: Table 7.13 Q114: Table 7.14 Q118: Table 7.13 Q120: Table 7.3 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents