Scenario 9.2
Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. The lead time from the plant to the wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant.
-Refer to Scenario 9.2. Which of the following situations results in the wholesaler's total cycle plus pipeline inventories amounting to 400 units?
A) The plant shipment lot size of 500 and plant-to-wholesaler lead time of 3 weeks
B) The plant shipment lot size of 400 and plant-to-wholesaler lead time of 3 weeks
C) The plant shipment lot size of 600 and plant-to-wholesaler lead time of 4 weeks
D) The plant shipment lot size of 400 and plant-to-wholesaler lead time of 2 weeks
Correct Answer:
Verified
Q36: Dependent demand items are those items for
Q37: Scenario 9.1
Shipments of Product A from a
Q38: Independent-demand items are those items for which
Q39: Scenario 9.2
Shipments of Product X from a
Q40: _ occurs when inventory is stolen by
Q42: Which of the following does not increase
Q43: What are the three types of inventory?
Q44: The primary lever to reduce anticipation inventory
Q45: Which of the following is not a
Q46: A _ lever is one that must
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents