Assume that a time-series forecast is generated for future demand and subsequently it is observed that the forecast method did not accurately predict the actual demand.Specifically,the forecast errors were found to be: Mean absolute percent error = 10%
Cumulative sum of forecast errors = 0
Which one of the statements concerning this forecast is TRUE?
A) The forecast has no bias but has a positive standard deviation of errors.
B) The forecast has a positive bias and a standard deviation of errors equal to zero.
C) The forecast has no bias and has a standard deviation of errors equal to zero.
D) The forecast has a positive bias and a positive standard deviation of errors.
Correct Answer:
Verified
Q23: Which one of the following is most
Q23: Which one of the following statements about
Q28: A bias error results from unpredictable factors
Q30: Table 8.1
The management of an insurance company
Q33: Which one of the following statements about
Q34: Aggregating products or services together generally decreases
Q36: _ methods use historical data on independent
Q37: Table 8.1
The management of an insurance company
Q39: _ analysis is a statistical approach that
Q40: Forecast error is found by subtracting the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents