Fig.7.2
Which one of the following statements regarding Figure 7.2 is TRUE?
A) Activity S cannot finish until activity T finishes.
B) Activity T cannot begin until activity U is completed.
C) Activity U cannot begin until activities S and T have been completed.
D) Activity V cannot begin until activity S has been completed.