A company could add $10,000 per week in revenues if the project depicted in Table 7.10 could be shortened. Table 7.10
Four possible options exist to crash activities: crash A by one week at a cost of $6,000;crash C by two weeks at a cost of $15,000;crash E by one week at a cost of $2,000;and crash I one week at a cost of $7,000.What is the maximum amount of additional profit that can be made by crashing an option (or options) ?
A) less than or equal to $4,000
B) greater than $4000 but less than or equal to $8,000
C) greater than $8000 but less than or equal to $12,000
D) greater than $12,000
Correct Answer:
Verified
Q84: The optimistic time is the probable time
Q90: Risk is a measure of the probability
Q91: A risk-management plan contains all identified risks
Q97: If a project has exactly one critical
Q97: Table 7.9 Q98: You are given the following information about Q108: To calculate the probability of completing a Q110: Table 7.13 Q116: Table 7.2 Q117: Information accuracy relative to the completeness of
![]()
All activity times for the project
![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents