Consider the activities,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow.
a.What is the expected time for activity B?
b.What is the variance for activity B?
c.Based on the calculation of estimated times,what is the critical path?
d.What is the estimated time of the critical path?
e.What is the activity variance along the critical path?
f.What is the probability of completion of the project before week 42?
Correct Answer:
Verified
b.
c.A-C...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q101: Table 7.14
You are responsible for managing a
Q106: Table 7.2 Q124: Which of these step comes first in Q130: _ is an attempt to reduce the Q131: What options do project managers have to Q132: A(n) _ identifies the key threats to Q133: The project manager and team can step Q134: To find the standard deviation of the Q137: The _ is the shortest time in Q139: Table 7.14
![]()
You are responsible for managing a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents