Scenario 2.5
A job consists of three distinct work elements that were timed with a highly accurate Swiss watch by a trained industrial engineer wearing a pristine white lab jacket and carrying an official-looking clipboard.Worker ratings were less inflated by the newness of the job elements to the worker than by the overall nervousness of the worker.The engineer recorded ten observations and assigned the performance rating that is recorded in the bottom row of the table under the corresponding work element.All recorded times are in seconds.
-Use the data in Scenario 2.5 to answer this question.If the rating factor is 10% and the allowance is 15%,what is the standard process time?
A) 110.69 seconds
B) 82.62 seconds
C) 109.27 seconds
D) 95.02 seconds
Correct Answer:
Verified
Q138: Highly customized job processes and processes that
Q143: Scenario 2.3
A job consists of three elements.
Q144: Scenario 2.3
A job consists of three elements.
Q147: Scenario 2.3
A job consists of three elements.
Q148: Scenario 2.2
Garman observes a worker assembling peanut
Q148: Garman observes a worker assembling peanut valves
Q154: Scenario 2.5
A job consists of three distinct
Q156: Scenario 2.5
A job consists of three distinct
Q157: Scenario 2.3
A job consists of three elements.
Q160: Scenario 2.1
Garman observes a worker assembling peanut
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents