The process capability measures Cp and Cpk differ because
A) only one ensures the process mean is centered within the limits.
B) Cp values above 1 indicate a capable process,Cpk values above 2 indicate a capable process.
C) both are identical.
D) Cp values for a given process will always be greater than or equal to Cpk values.
E) Cpk values for a given process will always be greater than Cp values.
Correct Answer:
Verified
Q63: Which of the following statements on acceptance
Q65: A nationwide parcel delivery service keeps track
Q66: An acceptance sampling plan's ability to discriminate
Q69: Which of the following is true regarding
Q70: The statistical process chart used to control
Q71: An operating characteristic (OC) curve describes
A) how
Q73: A run test is used
A) to examine
Q75: The normal application of a p-chart is
Q80: Acceptance sampling
A) is the application of statistical
Q235: Acceptance sampling's primary purpose is to:
A) estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents