Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One;$400
B) One;$6,800
C) Two;$1,000
D) Two;$5,000
E) One or two should be crashed;$1,400
Correct Answer:
Verified
Q50: The _ is the computed longest time
Q58: What is the basic difference between PERT
Q61: A local project being analyzed by PERT
Q68: A PERT project has 45 activities, 19
Q69: If an activity whose normal duration is
Q73: An activity on a PERT network has
Q76: A project being analyzed by PERT has
Q97: _ is a network technique using only
Q98: _ divides a project into more and
Q125: A network has been crashed to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents