Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q102: A network consists of the following list.Times
Q103: Consider the network described in the table
Q104: Pirmin's Bike Shop is behind on a
Q104: Briefly describe the concept of cost/time trade-off
Q107: Draw the AOA and AON networks for
Q109: A network consists of the activities in
Q110: Given the project within the table below
Q114: Describe in words how to calculate a
Q115: Briefly discuss what is meant by critical
Q119: What are the advantages of using PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents