A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. After line balancing, the largest possible assigned cycle time is ________ and the smallest possible assigned cycle time is ________ minutes.
A) 1.8; 1.4
B) 1.6; 0.9
C) 6.4; 2.4
D) 2.4; 0.9
E) none of these
Correct Answer:
Verified
Q81: A disadvantage of product-oriented layout is that
A)
Q83: Which of the following is a common
Q87: Which of these layouts is most suitable
Q88: An assembly line consists of 21 tasks
Q89: The main advantage of a product-oriented layout
Q90: Daily capacity of a product layout is
Q103: In assembly-line balancing,the theoretical minimum number of
Q288: Cycle time is computed as:
A) desired output
Q294: The central problem in product-oriented layout planning
Q300: A production line is to be designed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents