Question 61
Multiple Choice
The priority rule that sequences jobs using the smallest ratio of due date from today to processing time is
Question 62
Multiple Choice
When a set of jobs must pass through two workstations whose sequence is fixed, __________ is the sequencing rule most commonly applied.
Question 63
Multiple Choice
Which of the following are limitations of rules-based dispatching systems?
Question 64
Multiple Choice
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, what is the optimum sequence of jobs and the minimum time for completion of all jobs?
Question 65
Multiple Choice
Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from Today.
Question 66
Multiple Choice
Flow time represents the time
Question 67
Multiple Choice
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence?
Question 68
Multiple Choice
Which of the following dispatching rules tends to minimize job flow time?
Question 69
Multiple Choice
Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.
Question 70
Multiple Choice
Conventional MRP uses time buckets that do not recognize capacity limits, and in fact ignores capacity issues. A more realistic scheduling system that includes work center capacities and other resource availabilities is