Principles of Operations Management
Quiz 13: Aggregate Planning
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 21
Multiple Choice
Disaggregation
Question 22
Multiple Choice
Aggregate planning would entail which of the following production aspects at BMW for a 12 month period?
Question 23
Multiple Choice
Which of the following statements about aggregate planning is false?
Question 24
Multiple Choice
Which of the following would most likely fall under the scope of only an operations manager?
Question 25
Multiple Choice
Frito-Lay uses aggregate planning to match capacity with demand because of the __________ associated with its specialized processes.
Question 26
Multiple Choice
Planning tasks associated with loading, sequencing, expediting, and dispatching typically fall under
Question 27
Multiple Choice
Which of the following inputs helps an aggregate planner select the rate of output for a facility over the next 3 to 18 months?
Question 28
Multiple Choice
Which of the following is the term used for medium range capacity planning with a time horizon of three to eighteen months?
Question 29
True/False
Aggregate planning for fast food restaurants is very similar to aggregate planning in manufacturing, but with much smaller units of time.
Question 30
True/False
The transportation method of linear programming is an optimizing approach to aggregate planning.
Question 31
Multiple Choice
The planning tasks associated with staffing, production, inventory, and sub-contracting levels typically fall under
Question 32
True/False
The management coefficients model is a formal planning model built around a manager's experience and performance.
Question 33
Multiple Choice
Which of the following statements about aggregate planning is true?
Question 34
Multiple Choice
The objective of aggregate planning is to meet demand while __________ over the planning period.
Question 35
True/False
A hotel room that goes unrented and an airline seat that goes unsold are both examples of perishable inventory in services.
Question 36
True/False
Controlling the cost of labor in services involves quick response to consumer demand, on-call labor for unexpected demand, flexibility of labor for reallocation, and flexibility of hours or rate of output of individual workers.