Multiple Choice
Which of the following projects were completed by Bechtel?
Question 2
Multiple Choice
Ethical issues that may arise in projects large and small include:
Question 3
Multiple Choice
The phases of project management are:
Question 4
Multiple Choice
WBS stands for which of the following project management tools?
Question 5
Essay
A(n)________ is an organization formed to ensure that programs (projects)receive the proper management and attention.
Question 6
Multiple Choice
A project organization:
Question 7
Multiple Choice
Which of the following statements regarding Bechtel is true?
Question 8
True/False
One responsibility of a project manager is to make sure that the project meets its quality goals.
Question 9
Multiple Choice
Which of the following statements about Bechtel is true?
Question 10
True/False
Ethical issues that can arise in projects include gifts from contractors,pressure to mask delays with false status reports,and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.
Question 11
Essay
What are the three phases of a project? Describe each in a sentence or two.
Question 12
Multiple Choice
Which of the following is NOT one of the phases of project management?
Question 13
True/False
One phase of a large project is scheduling.
Question 14
Multiple Choice
The project organization works best when which of the following conditions are satisfied? I.Work tasks can be defined with a specific goal and deadline. II.The job is typical and familiar to the existing organization. III.The work contains interrelated tasks requiring specialized skills. IV.The project is temporary but unimportant to long-term organizational success. V.The project cuts across organizational lines.
Question 15
True/False
Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.
Question 16
Multiple Choice
Match the following steps in Microsoft's development of Windows 8 to their respective WBS level. Step Level Develop Windows 8 Operating System ? System Testing ? Compatible with Windows 7 ? Develop GUI's ? Module Testing ?