A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q87: Analysis of a PERT problem shows the
Q88: Which of the following statements regarding PERT
Q90: In a PERT network, non-critical activities that
Q91: An activity on a PERT network has
Q93: A project being analyzed by PERT has
Q97: Contract requirements state that a project must
Q98: An activity on a PERT network has
Q100: A local project being analyzed by PERT
Q107: How is the expected completion time of
Q108: A project whose critical path has an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents