Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One;$400
B) One;$6,800
C) Two;$1,000
D) Two;$5,000
E) One or Two should be crashed;$1,400
Correct Answer:
Verified
Q109: Two critical path activities are candidates for
Q110: Three critical path activities are candidates for
Q112: In project management, crashing an activity must
Q113: What was the name of the construction
Q117: If an activity whose normal duration is
Q118: A network consists of the following list.Times
Q120: Shortening the project's duration by deleting unnecessary
Q120: If an activity whose normal duration is
Q125: A network has been crashed to the
Q127: Identify several advantages of using PERT (and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents