Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q108: Pirmin's Bike Shop is behind on a
Q109: Two critical path activities are candidates for
Q109: A project manager is interested in crashing
Q113: What was the name of the construction
Q114: Two critical path activities are candidates for
Q117: If an activity whose normal duration is
Q120: Shortening the project's duration by deleting unnecessary
Q122: Which of the following is NOT a
Q127: Identify several advantages of using PERT (and
Q129: _ is decreasing activity time in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents