Contingency costs in the project costs estimate, also referred to as ____, are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time (redesigns) , or a high probability or high impact risk that may occur.
A) auxiliary funds
B) withholding
C) reserves
D) capital funds
Correct Answer:
Verified
Q21: A cost is determined for each period,
Q22: Allocating total project costs for the various
Q23: Travel costs in the project costs estimate
Q24: Large projects would have charge codes for
Q25: Costs related to _ are for outsourced
Q27: The _ for the entire project or
Q28: To keep track of _, it's necessary
Q29: Once a total budgeted cost has been
Q30: It is important to use the _
Q31: The project cost estimate is allocated to
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents