Solved

Contingency Costs in the Project Costs Estimate, Also Referred to as ____

Question 26

Multiple Choice

Contingency costs in the project costs estimate, also referred to as ____, are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time (redesigns) , or a high probability or high impact risk that may occur.


A) auxiliary funds
B) withholding
C) reserves
D) capital funds

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents