To Keep Track of ____, It's Necessary to Set Up

Question 28

Multiple Choice

To keep track of ____, it's necessary to set up a system to collect, on a regular and timely basis, data on funds actually expended.


A) budgeted cost of work scheduled
B) planned cost of the project
C) actual cost on a project
D) budgeted cost of work performed